Estimate of Impact Fees on the Cost of Construction

This estimate is based on the information provided by the City of Holiet that was included in their press release at the time the school facility impact fees were announced. According to Joliet, 10,000 homes per year are projected to be built in ten Will County communities over the next 15 years resulting in aggregate impact fees of $800,000,000.

 
10,000
houses built per year
 
15
years
 
150,000
houses
Total impact fee
$800,000,000
 
 
150,000
houses
 
$5,333
impact fees per house
Projected housing build out:
 
Plainfield
28,368
 
Joliet
7,806
 
 
36,174
houses
Impact fee per house
$5,333
 
Impact fees for District 202
$192,928,000
 
Projected construction costs
$1,043,578,000
 
   Less schools constructed:
 
   - Lincoln Elementary
$12,000,000
 
   - New Middle School
$17,000,000
 
Projected future costs
$1,014,578,000
 
Impact fees for District 202
$192,928,000
 
NET
$821,650,000
 
Say
$800,000,000
 

|
|
| |
|
|
|
|